EnergyBeira Rio SHP
Full construction management and owner's engineering on an 18 MW small hydropower plant in northern Paraná.
Detailed design of a labyrinth side spillway with 4D BIM modelling, for Klabin in Telêmaco Borba.

Detailed design of the side spillway of the Harmonia dam in Telêmaco Borba, Paraná.
The chosen solution was a 46.8 m labyrinth spillway with a 144.05 m chute. The design was developed in BIM, with a 4D model linking geometry to the construction schedule.
EnergyFull construction management and owner's engineering on an 18 MW small hydropower plant in northern Paraná.
EnergyFull construction management and owner's engineering on a 26 MW small hydropower plant in north-western Minas Gerais.
EnergyFull construction management and owner's engineering on a 14 MW small hydropower plant in Goiás.
Tell us the technical challenge and we will come back with the right team to assess it.